Project:
Construction procedure complex Wolkramshausen, track section 6343 Hann. Münden – Halle (Saale), two track electrified main line

Service period:
2014 – 2016

Project client:
DB ProjektBau GmbH

Project volume:
€ 43,000,000

Project description

In the area of the track section Nordhausen – Wolkramshausen, the substructure/superstructure replacement (2 track sections) was carried out, incl. reconstruction of cable container systems. 2 supporting walls were created as support pile walls, 4 railway flyovers were renovated, the cycle paths on 3 railway flyovers were replaced, the cantilever arm, the cantenary system and 30 masts of the overhead contact line system were reconstructed.

At Wolkramshausen train station, the substructure/superstructure replacement (4 track sections, alternating reconstruction of 7 points), the rebuilding of 3 supporting walls as support pile walls, and a partial rebuilding of the overhead contact line system were carried out.

The measure also includes the rebuilding of electronic signal box A, FMA, BMA MAS 90 with new safety technology, the manufacture of cable laying and cable connection electronic signal box A – electronic signal box Z (35km), the erection of 3-point heating stations and a NEA station (16 2/3 Hz) and rebuilding the marshalling area illumination, platform 1 and the cable container systems.

Also, 3 further railway crossings were recabled, safety/superstructure technology adjustments and overhead contact line changes.

Engineering services

  • Project management Carrying out superstructure/substructure, other construction
  • Preparation for implementation, implementation, project completion
  • Plan coordination
  • Creation and continuation of commissioning concept