Project:
New Terminal 3 building at Frankfurt Airport

Service period:
2007 – 2025

Project client:
Fraport AG

Project description

Terminal 3 forms the structural expansion in the southern area of the airport and consists of approximately 10 sub-projects and numerous measures in the surrounding area. Once fully developed, it will have a capacity of 25 m passengers per year. A new personal transport system will create a link to the north site of Terminal 1 and 2.

The following uses are planned in the terminal:

- Check-in facilities

- Security, customs and passport controls

- Shops and catering outlets

- Gate and lounge areas

- Baggage check-in facilities

- Car park with 8,500 parking spaces

Key focuses of the project are the

- high technical complexity of carcass, building services and expansion

- integration of additional requirements over years of planning

- extremely comprehensive integration and coordination of the large number of specialist planners

- integration of the baggage conveying technology (20 km conveying route in four sub-projects)

Engineering services

  • Project management, all action areas A - E and PS 1 - 3 according to AHO book 9
  • Extended quality inspection of planning
  • Document management